Question: Figure 8 - 4 Project Crashing Information Consider the project crashing information presented in Figure 8 - 4 . What is the total cost to

Figure 8-4 Project Crashing Information
Consider the project crashing information presented in Figure 8-4. What is the total cost to complete this project in 7 days if crashed in the most cost efficient manner?
Group of answer choices
$ 240
$ 180
$ 270
$ 220