Question: Fill in the blank: _ _ _ _ _ is the method where a project manager reviews all individual tasks and rolls the tasks into

Fill in the blank: _____ is the method where a project manager reviews all individual tasks and rolls the tasks into manageable chunks that lead to a milestone.
1 point
Goal scheduling
Bottom-up scheduling
Team scheduling
Top-down scheduling