Question: FINAL CLASS WORK Suppose you are considering crashing a project. The projects network is as follows, along with a table identifying its critical activities and

FINAL CLASS WORK

Suppose you are considering crashing a project. The projects network is as follows, along with a table identifying its critical activities and the crash costs for all tasks.

What is the cost of the project?

Which activities are the best candidates for crashing?

What is the expected duration of the project once it has been fully crashed?

What will the cost of the fully crashed project be?

Normal

Crashed

Activity

Duration

Cost (in U.S. dollars)

Duration

Cost

(in U.S. dollars)

A

4 days

1,000

3 days

2,000

B

6 days

1,800

3 days

3,000

C

4 days

2,500

3 days

4,000

D

9 days

2,700

6 days

6,500

E

8 days

2,400

6 days

4,500

F

5 days

3,500

3 days

7,000

G

2 days

2,400

1 day

3,000

Total costs

=

$16,300

$30,000

Project Activities and Costs (Normal vs. Crashed)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!