Question: Final Exam ME 4 7 7 Date 1 0 / 0 2 / 2 0 2 4 Time allowed 2 . 0 0 hrs Q#

Final Exam ME 477 Date 10/02/2024 Time allowed 2.00 hrs
Q# 1
a-what is the project?
b-what is the triple constraint of the project?
c-who are the key project stock holder?
d-who is the project manger?
why crashing the project?
Q#2) Construct an activity on arrow network based on the activity descriptions below. Show all your work. Label activities
-Activities H, R2, T1 start the project.
Activity T2 can start when Activities HnE1 and S are completed.
-Activity E1,also depends on Activity R2.
-Activity X follows Activity H and precedes Activity L.
-Activity E is preceded by Activities T2 and P1.
-The predecessors to Activity G are Activities L, T2 and P1.
-The successors to Activity T1 are Activities E1, S, W and D2.
-Activity P1 cannot begin until Activity W is finished.
-Activity P2 and F follow Activities W and D2, and precede Activities E and R1.
Activity 02 depends on T2 and P1, and precedes Activity L
Q#3 Find the critical path ? find the slack value? Draw the Gantt chart.
 Final Exam ME 477 Date 10/02/2024 Time allowed 2.00 hrs Q#

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!