Question: Find: 1 . The AOA network and the path with the longest expected duration. 2 . All event slacks. 3 . Critical path to event

Find:
1. The AOA network and the path with the longest expected duration.
2. All event slacks.
3. Critical path to event D.
4. The probability of completing the path with the longest expected duration in 14 days.
5. The effect if CD slips to 6 days; to 7 days; to 8 days.
Activity TE
AB 1
AC 2
AD 3
DC 4
CB 3
DE 8
CF 2
BF 4
IJ 2
CE 6
EF 5
FG 10
FH 11
EH 1
GH 9
EJ 3
GI 8
HJ 6
a. Draw the AOA diagram.
b. Find the critical path.
c. Find the expected project completion time.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!