Question: Find a workforce plan using the level strategy that allows for no delay in service. Overtime can be used and undertime should be minimized. 1
Find a workforce plan using the level strategy that allows for no delay in service. Overtime can be used and undertime should be minimized.
| 1 | 2 | 3 | 4 | |
| Forecasted Demand | 3200 | 6800 | 5200 | 4800 |
| Workforce Level | ||||
| Undertime hours | ||||
| Overtime hours | ||||
| Utilized time hours | ||||
| # of Hires | ||||
| # of Layoffs | ||||
| Utilized time cost | ||||
| Undertime cost | ||||
| Overtime Cost | ||||
| Hiring cost | ||||
| Layoff cost |
1a. What is the workforce level for this plan using level strategy?
1b. What is the undertime hours in the 3rd quater?
1c. What is the overtime hours in the 2nd quater?
1d. What is the utilized hours in the 2nd quater?
1e. What is the hire or layoff plan in the first quater?
1f. What is the undertime cost in the first quater?
1g. What is the total cost of this level strategy?