Question: Find NPV and IRR for both the projects. Year Project A Project B 0

Find NPV and IRR for both the projects.  

Year     Project A         Project B
0             -200$             -150$
1              200$                50$
2              800$               100$
3             -800$               150$

Calculate IRR by finding the NPV first with a rate of return of 10%. Then calculate positive NPV, then calculate negative NPV. And then find the IRR using the formula,