Question: Find text or tools Construct a Gantt chart similar to the one in Figure 6 . 1 0 using the following data: When will task
Find text or tools
Construct a Gantt chart similar to the one in Figure using the following data: When will task G be completed?
tableTaskStart Time wksDuration wksABCDEFG
How must the Gantt chart you drew in problem be changed if you were told that and D could not begin until B was completed and that G could not begin until C was completed? What happens to the project completion time?