Question: 25. How must the Gantt chart you drew in problem 24 be changed if you were told that C andD could not begin until B
25. How must the Gantt chart you drew in problem 24 be changed if you were told that C andD could not begin until B was completed and that G could not begin until C was completed?What happens to the project completion time?


24. Construct a Gantt chart similar to the one in Figure 6.10 using the following data: When will task G be completed? Task Start Time [wks) Duration [wks] NOONNOOBasic design Hardware design A Hardware design B Drawings B Software specifications L Parts purchase B M Parts purchase A N Drawings A Installation drawings Work packages Software purchase Delivery B Delivery A Software delivery NEXEC4030 00 Assembly A Assembly B Test A Test B Final Installation Final test 4 B 12 16 20 24 28 32 36 40 44 4E Figure 6.10 Gantt chart for LOGON project