Question: Find the critical path: Activity Designation Immediate Predecessor Time in Days Disassemble both machines A None 3 Wash machine 1 B A 3 Wash machine
Find the critical path:
Activity Designation Immediate Predecessor Time in Days
Disassemble both machines A None
Wash machine B A
Wash machine C A
Adjust machine D B
Adjust machine E C
Assemble both machines F D and E
Final test G F