Question: Find the critical path: Activity Designation Immediate Predecessor Time in Days Disassemble both machines A None 3 Wash machine 1 B A 3 Wash machine

Find the critical path:
Activity Designation Immediate Predecessor Time in Days
Disassemble both machines A None 3
Wash machine 1 B A 3
Wash machine 2 C A 3
Adjust machine 1 D B 4
Adjust machine 2 E C 2
Assemble both machines F D and E 1
Final test G F 2