Question: Find the critical path. Compute the slack Assign Tasks Programming Program Test System Test ID: 2 Dur 5 ID: 4 Dur Start Day 76 ID:
Find the critical path. Compute the slack
Assign Tasks Programming Program Test System Test ID: 2 Dur 5 ID: 4 Dur Start Day 76 ID: 6 Dur 10 ID: 9 Dur 12 Develop Plan User Test Write User Manual ID: 11 ID: 1 Dur: 1 ID: 7 Dur 12 Obtain Hardware Install Hardware User Training ID: 3 Dur 10 ID: 5 Dur 8 ID: 10 Dur 5 Convert Files ID: 8 Dur 15