Question: Find the critical path for the project defined below. Crash the project assuming you have $1500 to spend and that activities cannot be shorter than

Find the critical path for the project defined

Find the critical path for the project defined below. Crash the project assuming you have $1500 to spend and that activities cannot be shorter than their minimum durations. Note that activity B cannot be crashed. Try to achieve the greatest reduction in project duration for the least amount spent. MINIMUM PRECEDENT CRASH ACT. DURATION DUR ACTIVITY COST/DAY A 3 2 $400 B 3 3 A 5 A 2 4 D B 4 7 $200 $200 $300 $100 $400 $100 E 5 B, C F 11 3 G 9 7 D,E,F