Question: Find the project completion time for the project with following sequence of activities: Activity Predecessor Time A 8 B 3 A 7 D A, B

Find the project completion time for the project

Find the project completion time for the project with following sequence of activities: Activity Predecessor Time A 8 B 3 A 7 D A, B 4 E C, D 4