Question: Firewall Project XT. Using the complexity weighting scheme and the function point complexity weighted table shown below, estimate the total function point count. Assume historical

Firewall Project XT. Using the "complexity weighting" scheme and the function point complexity weighted table shown below, estimate the total function point count. Assume historical data suggest five function points equal on person month and six people can work on the project.

Complexity Weight Table
Number of inputs 10 Rated complexity low
Number of outputs 20 Rated complexity average
Number of inquiries 10 Rated complexity average
Number of files 30 Rated complexity high
Number of interfaces 50 Rated complexity high

a. What is the estimated project duration?

b. If 20 people are available for the project, what is the estimated project duration?

c. If the project must be complete in six months, how many people will be needed for the project?

The total function point count is:

Complexity Weighting
Element Count Low Average High Total
Inputs 10 10 x 2 = 20
Outputs 20 20 x 6 = 120
Inquiries 10 10 x 4 = 40
Files 30 30 x 12 = 360
Interfaces 50 50 x 15 = 750
TOTAL = 1,290

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!