Question: Firewall Project XT. Using the complexity weighting scheme and the function point complexity weighted table shown below, calculate the total function point count. Assume historical

Firewall Project XT. Using the complexity weighting scheme and the function point complexity weighted table shown below, calculate the total function point count. Assume historical data suggest 6 function points equal one person-month and 7 people can work on the project. (Round the final answers to the nearest whole numbers.)