Question: Fite Co is designing a product layout for a new product. They plan to use this production line 10 hours a day in order to
Fite Co is designing a product layout for a new product. They plan to use this production line 10 hours a day in order to meet forecasted demand of 900 units per day. The following table describes the tasks necessary to produce this product:
Task Time (seconds) Predecessor
A 34 None
B 20 A
C 10 B
D 16 B
E 10 C
F 24 D, E
G 38 F
STEP 1
Without considering forecasted demand (if you ignored demand), what is the minimum possible cycle time and the "Herbie" for this production line?
STEP 2
For output to equal forecasted demand, what is the minimum number of workstations needed?
STEP 3
If the company wants the output rate to be equal to demand, which activities would be assigned to which workstation?
STEP 4
If the company wants the output rate to be equal to demand, what would be the efficiency of this line with the minimum number of workstations?