Question: PERT activity has an early start ( ES ) date of Monday and an estimated time of 3 days. Its early finish ( EF )

PERT activity has an early start (ES) date of Monday and an estimated time of 3 days. Its early finish (EF) date should be? Assume the task can start at 8am on the early start date. A. Monday b. ThursdayO. Tuesday d. Friday e. Wednesday? Assume the task can start