Question: Five activities are candidates for crashing on a computer security project. Activity details are on the following table: Activity Predecessor Normal Normal Crash Crash Time

Five activities are candidates for crashing on a computer security project. Activity details are on the following table: Activity Predecessor Normal Normal Crash Crash Time Cost Time Cost A -- 20 days $1000 8 days $1480 B -- 24 days $1200 20 days $1400 C -- 14 days $700 7 days $1190 D A 10 days $500 6 days $820 E C 11 days $550 5 days $730 - How much could you crash this project? How much would it cost? - How would you best crash it by 5 days? By 10 days? - Please make a graph of project length vs. cost