Question: Five activities are candidates for crashing on a computer security project. Activity details are on the following table: Activity Predecessor Normal Normal Crash Crash Time
Five activities are candidates for crashing on a computer security project. Activity details are on the following table:
Activity Predecessor Normal Normal Crash Crash
Time Cost Time Cost
A -- 20 days $1000 13 days $1420
B -- 24 days $1200 20 days $1400
C -- 14 days $700 7 days $1190
D A 10 days $500 6 days $1060
E C 11 days $550 5 days $730
*Please create a network diagram*
How much could you crash this project? How much would it cost?
How would you best crash it by 5 days? By 10 days?
Please make a graph of project length vs. cost