Question: Five batch jobs A through E arrive at a computer center at almost the same time. They have estimated running times of 1 0 ,

Five batch jobs A through E arrive at a computer center at almost the same time. They have
estimated running times of 10,6,2,4, and 8 minutes. Their priorities are 3,2,1,4 and 5
respectively, with 5 being the highest priority. For each of the following scheduling algorithms,
determine the mean process turnaround time. Turnaround time = completion time - arrival
time. Ignore process switching overhead. Also, make a Gantt chart for each question
Round robin
Priority scheduling
First come first served (run in order 10,6,2,4,8).
Shortest job first.
For (1) assume the system is multi-programmed, and that each job gets its fair share of the
CPU ( quantum time is: 4ms). Question 1 is preemptive.
For (2) through (4) assume that only one job at a time runs until it finishes. All jobs are
completely CPU-bound. Questions 2-4 are non-preemptive.
 Five batch jobs A through E arrive at a computer center

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Databases Questions!