Question: Five customers brought in computers to be repaired to a small shop. Estimated repair times (in days) and dates promised are given below. Due dates
Five customers brought in computers to be repaired to a small shop. Estimated repair times (in days) and dates promised are given below. Due dates were set based on available technicians; however, one technician had a medical emergency and will be unavailable for at least two weeks, so processing times were adjusted.
| Customer Job | 1 | 2 | 3 | 4 | 5 |
| Processing Time (Days) | 4 | 5 | 1 | 7 | 3 |
| Due Date (Days) | 3 | 5 | 2 | 10 | 6 |
Use the EDD rule to determine the EDD sequence.
- The EDD sequence, sorted by customer job is 4-1-2-3-5
- The EDD sequence, sorted by customer job is 1-2-3-4-5
- The EDD sequence, sorted by customer job is 3-1-2-5-4.
- The EDD sequence, sorted by customer job is 3-1-4-2-5
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock