Question: Five jobs are required to be completed in a two - machine flow shop and their respective needed times areshown in the next table. Each

Five jobs are required to be completed in a two-machine flow shop and their respective needed times areshown in the next table. Each job must begin with machine A and finish with machine B.Time (minutes)Job Machine A Machine B156234369478592
a. Determine the sequence that will minimize the make-span.
b. Construct a load Gantt chart for the resulting sequence and find machine As idle time.
c. For the sequence determined in part a, can machine As idle time be reduced by splitting some jobsin half? If so, which jobs?
d. Split jobs 3 and 5 and draw the new load Gantt chart.