Question: Five jobs are to be processed on one machine. If the jobs are processed in the FCFS order 1 - 2 - 3 - 4

Five jobs are to be processed on one machine. If the jobs are processed in the FCFS order 1-2-3-4-5, compute the start time and flow time for each job:Five jobs are to be processed on one machine. If the jobs are processed in the FCFS order 1-2-3-4-5, compute the start time and flow time for each job:
Fill the following table. If your answer is zero, enter "0".
Job 12345
Processing time 591102
Fill the following table. If your answer is zero, enter "0".
 Five jobs are to be processed on one machine. If the