Question: five jobs are to be processed on one machine. if the jobs are processed in the FCFS order 1-2-3-4-5, compute the start time and flow
five jobs are to be processed on one machine. if the jobs are processed in the FCFS order 1-2-3-4-5, compute the start time and flow time for each job.
Want to do 4 Five jobs are to be processed on one machine. If the jobs are processed in the FCFS order 1-2- 3-4-5, compute the start time and flow time for each job. Job Processing time 1 2 3 8 3 5 u w 4 5 9 4 9 Job Sequence (0 Start Time (sil. Processing Time (P) Flow Time (S+P) 0 1 2 3 8 11 16 25 8 3 5 9 4 4 5