Question: Five jobs are to be processed through a single machine. The processing times and due dates are given here. Job 1 2 3 4 5

Five jobs are to be processed through a single

Five jobs are to be processed through a single machine. The processing times and due dates are given here. Job 1 2 3 4 5 3 6 8 4 4 Processing Time Due Date 4 8 12 21 15 Assume that the following precedence relationships must be satisfied: 1-4 and 2-3. Determine the sequence in which these jobs should be done in order to minimize the maximum lateness subject to the precedence restrictions