Question: Five operators are involved in a work station, each working eight hours a day in the only shift dedicated to the manufacture of gears. They

Five operators are involved in a work station, each working eight hours a day in the only shift dedicated to the manufacture of gears. They work 22 days a month. Due to production process issues, each operator spends 0.4, 0.1, 0.3, 0.2 and 0.6 hours per shift, respectively, in handling materials. Determine the monthly material handling percentage