Question: Five welding jobs are waiting to be processed. Their processing times and due dates are given below. Using the First Come - First Served dispatching

Five welding jobs are waiting to be processed. Their processing times and due dates are given below. Using the First Come - First Served dispatching rule, What is the Total Flow Time? All dates are specified as days from today.
Job Procssing Job due date Time (days)(days)
A 217
B 614
C 711
D
7
15
E 6
22
 Five welding jobs are waiting to be processed. Their processing times