Question: Five welding jobs are waiting to be processed. Their processing times and due dates are given below. Using the First Come - First Served dispatching
Five welding jobs are waiting to be processed. Their processing times and due dates are given below. Using the First Come - First Served dispatching rule, What is the Total Flow Time? All dates are specified as days from today.
Job Processing Time (days) Job due date (days)
A 2. 17
B. 3. 14
C. 11. 11
D. 5. 15
E. 3. 22
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts