Question: Five welding jobs are waiting to be processed. Their processing times and due dates are given in Table Q5(b). Job A D E Table Q5(b)

Five welding jobs are waiting to be processed.

Five welding jobs are waiting to be processed. Their processing times and due dates are given in Table Q5(b). Job A D E Table Q5(b) Processing Time (days) Job due date (days) 8 2 6 8 18 3 15 9 23 (i) Using the first come first served rule, determine the order which the jobs should be processed. All dates are specified as days from today. (11 marks) (ii) Determine the average completion time. (2 marks) (iii) (2 marks) Determine the utilization metric. Determine the average number of jobs in the system. (iv) (2 marks)