Question: Fleming and Koppelman ( p . 1 1 1 ) describe six key events that accompany procurements on projects. They are the following: The project
Fleming and Koppelman p describe six key events that accompany procurements on projects. They are the following:
The project manager must define the items to be procured. This is usually done by conducting a "make or buy" analysis, typically under the direction of the project manager, or staff.
They must define the technical requirements of the purchases. This is done by the engineering or design organizations and results in a procurement specification.
They must request that a procurement be made by issuing a formal purchase requisition, which is normally done by the project manager, or staff.
A formal order to buy must be given by the buyer, who issues a contract or purchase order.
The purchased items must be received, inspected, accepted, or the purchased services verified. This consists of taking physical possession of the commodities andor of verifying their satisfactory completion. Various functions perform this work.
Payment must be made for the purchased goods. The accounts payable organization must issue a check to the seller, and the costs recorded on the accounting ledger.
Considering ONE of these events, describe the implications for EVM. How can the work described in this event be separated into distinct tasks? How can task completion be estimated in terms of costs? In terms of earned value?
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock