Question: Float data is missing from two of the tables. Complete this after you have created your network diagram. Activity Duration Predecessors A 3 5 A

Float data is missing from two of the tables.

Float data is missing from two of the tables. Complete this after you have created your network diagram.

Activity Duration Predecessors A 3 5 A 7. A 3. IoT mono , 5 B 4 D G 2 H. 5 E, F, G Activity Duration ES EF LS LF Slack A 3 O 3. O 0 3 B 5 3 8 5 10 C 7 3 10 3 D 3 10 E 5 3 10 13 10 13 13 12 17 17 13 17 8 Tu I ALIN F 4. 13 G 2 10 12 15 17 H 5 17 22 17 22 Resource Hours Needed Total Float Total Resources Required Activity Duration per Week A 3 weeks 6 18 B 5 weeks 4 20 C 7 weeks 4 28 D 3 weeks 6 18 E | | | IN 2 5 weeks 4 weeks 10 F 4 16 G 2 weeks 3 6 I a 30 5 weeks 6 Total 146

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!