Question: Following a lean approach to a level and balanced schedule what batch quantities per cycle would result using the following monthly requirements data? Note: Assume

Following a lean approach to a level and balanced schedule what batch quantities per cycle would result using the following monthly requirements data? Note: Assume set up times (changeover times) are negligible.
Question 4Select one:
a.
500 As,200 Bs,300 Cs, and 100 Ds per cycle
b.
5 As,2 Bs,3 Cs, and 1 D per cycle
c.
5,000 As,2,000 Bs,3,000 Cs, and 1,000 Ds per cycle
d.
Approximately 227 As,91 Bs,136 Cs, and 45 Ds per cycle
e.
50 As,20 Bs,30 Cs, and 10 Ds per cycle