Question: following table. begin{tabular}{ccc} hline Task & Performance Time (minutes) & Task Must Follow Task Listed Below hline A & 1 & B &

following table. \begin{tabular}{ccc} \hline Taskfollowing table. \begin{tabular}{ccc} \hline Task

following table. \begin{tabular}{ccc} \hline Task & Performance Time (minutes) & Task Must Follow Task Listed Below \\ \hline A & 1 & \\ B & 2 & \\ C & 1 & A \\ D & 2 & B, C \\ E & 3 & D \\ F & 2 & E \\ \hline \end{tabular} a. Given the demand, what is the cycle time for this operation? minutes b. What is the theoretical minimum number of work stations? c. What is the actual number of stations? d. What is the idle time? minutes e. What is the overall actual efficiency of the assembly line

Step by Step Solution