Question: Following table shows MPS for a specific product ( P 1 ) for twelve months. table [ [ , Month,, ] , [ 1
Following table shows MPS for a specific product for twelve months.
tableMonth,,MPS
This product requires standard hours of machinelabor time, as shown in the bill of labor BOL below. There are three workstations, WC: Turning, WC : Milling and WC: Drilling.
tableResourceWCWCWCTotalTime hours
a Calculate required capacity for each workstation in each period by using capacity planning using overall factors CPOF
b Company decided to produce a new product P with following MPS and BOL.
tableMonth,,MPS
tableResourceWCWCWCTotalTime hours
Consider both products and and calculate required capacity in each workstation by the Bill of Labor Approach.
c Resource profiles for products and are given below.
tableProduct PMonths before due dateWCWCWC
tableProduct PMonths before due dateWCWCWC
Calculate the required capacity in each workstation by using the Resource Profile Approach.
Draw a graph to illustrate the machine load report of the workstations.
What should the minimum available capacities of the workstations?
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock