Question: For 106 consecutive days, a process engineer has measured the temperature of champagne bottles as they are made ready for serving. Each day, she took
| For 106 consecutive days, a process engineer has measured the temperature of champagne bottles as they are made ready for serving. Each day, she took a sample of 8 bottles. The average across all 848 bottles (106 days, 8 bottles per day) was 59 degrees Fahrenheit. The standard deviation across all bottles was 0.7 degrees Fahrenheit. | |||
| When constructing an X-bar chart, what would be the center line? | |||