For a department, the standard overhead rate is Rs.2.50 per hour and the overhead allowances are as
Fantastic news! We've Found the answer you've been seeking!
Question:
For a department, the standard overhead rate is Rs.2.50 per hour and the overhead allowances are as follows:
Activity Level (Hours) Budgeted Overhead Allowance
3,000 Rs.10,000
7,000 Rs.18,000
11,000 Rs.26,000
In a period, the activity level of the said department was 10,000 hours and the actual overheads incurred were Rs.22,000.
Required:
i) The fixed cost
ii) The standard activity level on which the standard overhead rate has been fixed.
iii) Budget variance
iv) Idle capacity variance
v) Overall variance with check (proof)