Question: For a garage construction project, there are not enough resources available to complete some of the activities. The project manager still wants to keep the

For a garage construction project, there are not enough resources available to complete some of the activities. The project manager still wants to keep the same scope as agreed with the sponsor without adding an extra budget.
Which one of the following is the best course of action for the above scenario?
Group of answer choices
hire additional resources
accelerate the activities that have enough resources to free the needed resources
delay non-critical path activities until the resource is available
start the tasks on the day they are scheduled to start and expect unassigned resources from other activities to complete the work
reallocate resources based on the remaining budget

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!