Question: For a garage construction project, there are not enough resources available to complete some of the activities. The project manager still wants to keep the
For a garage construction project, there are not enough resources available to complete some of the activities. The project manager still wants to keep the same scope as agreed with the sponsor without adding an extra budget.
Which one of the following is the best course of action for the above scenario?
start the tasks on the day they are scheduled to start and expect unassigned resources from other activities to complete the work
hire additional resources
delay noncritical path activities until the resource is available
accelerate the activities that have enough resources to free the needed resources
reallocate resources based on the remaining budget
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock