Question: For a given activity, Optimistic time= 17 days, Most likely time- 29 days and Pessimistic time= 47 days Calculate: a. Weighted average activity time and

For a given activity, Optimistic time= 17 days, Most likely time- 29 days and Pessimistic time= 47 days Calculate: a. Weighted average activity time and variance

b. From the above calculation, use the weighted average time and variance, calculate

Probability of completing the project greater than 25 days

Probability of completing the project less than greater than 30 days

Probability of completing the project between 25 and 30 days