Question: For a given activity, Optimistic time= 17 days, Most likely time= 29 days and Pessimistic time= 47 days Calculate a. Weighted average activity time and

For a given activity,

Optimistic time= 17 days, Most likely time= 29 days and Pessimistic time= 47 days

Calculate

a. Weighted average activity time and variance

b. If the scheduled duration is 60 days, weighted average activity time is 64 days, and the variance is 36 days. What is the probability completing the project by time period 60 days

Use the following Z-Table

z -0.09 -0.08 -0.07 -0.06 -0.05 -0.04 -0.03 -0.02 -0.01 -0.00

-0.9 .1611 .1635 .1660 .1685 .1711 .1736 .1762 .1788 .1814 .1841 -0.8 .1867 .1894 .1922 .1949 .1977 .2005 .2033 .2061 .2090 .2119 -0.7 .2148 .2177 .2206 .2236 .2266 .2296 .2327 .2358 .2389 .2420 -0.6 .2451 .2483 .2514 .2546 .2578 .2611 .2643 .2676 .2709 .2743 -0.5 .2776 .2810 .2843 .2877 . 2912 .2946 .2981 .3015 .3050 .3085

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!