Question: For a given project activity, the optimistic duration estimate is 15, the pessimistic duration estimate is 36 and the most likely duration estimate is 18.

For a given project activity, the optimistic
For a given project activity, the optimistic duration estimate is 15, the pessimistic duration estimate is 36 and the most likely duration estimate is 18. As we dealt with this activity in finding our critical path, what would we use as an estimated duration for it? (Round to 2 decimal places)