Question: For a given project, duration and resource requirements are given below Activity Duration (weeks) Machines Crew size (Men) 1-2 7 2 20 1-3 7 2
- For a given project, duration and resource requirements are given below
Activity Duration (weeks) Machines Crew size (Men)
1-2 7 2 20
1-3 7 2 20
2-3 8 3 30
2-4 6 4 30
3-6 9 2 20
4-5 3 2 20
5-6 5 2 20
Resources AVAILABILITY: (A) Machines 4 (B) Men 40
- Draw the network diagrm, identify the critical path assuming that there are no resource constraints.
- Draw the time scale network as per EST and level the resources
- Find the project completion time under the given resource constraint.