Question: For a given project, duration and resource requirements are given below Activity Duration (weeks) Machines Crew size (Men) 1-2 7 2 20 1-3 7 2
For a given project, duration and resource requirements are given below Activity Duration (weeks) Machines Crew size (Men) 1-2 7 2 20 1-3 7 2 20 2-3 8 3 30 2-4 6 4 30 3-6 9 2 20 4-5 3 2 20 5-6 5 2 20 Resources