Question: For a large fill operation, it was decided to improve 8 m thick clay layer which is sandwiched between sand layers by preloading technique. The

For a large fill operation, it was decided to improve 8m thick clay layer which is
sandwiched between sand layers by preloading technique. The average permanent
load on the clay layer due to preloading will increase to 85kNm2. The average
effective overburden pressure on the clay layer before the fill operation is 120kN?
m2For the clay layer, which is normally consolidated and drained at top and bottom,
given: Cc=0.27,e0=1.02,Cv=0.52m2? month. Determine the following: (a) The
primary consolidation settlement of the clay layer caused by the addition of the
permanent load, (b) The time required for 80% of primary consolidation settlement
under the additional permanent load only and (c) The temporary surcharge that will
be required to eliminate the entire primary consolidation settlement in 12 months by
the pre-compression technique.
For a large fill operation, it was decided to

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Civil Engineering Questions!