Question: Q 1 . ( a ) A field compaction control test was conducted on a compacted fill. The mass of the material removed from the

Q1.(a) A field compaction control test was conducted on a compacted fill. The mass of the material removed from the hole was 1800g and the volume of the hole was found to be 900cm3. A small sample of the soil lost 16g in the drying test and the mass remaining after drying was 100g. The laboratory control test results are shown in the figure. (30%)(i) If end-product specification requires 95% relative compaction and =(optimum -1%) to (optimum +1%), determine the acceptability of the field
compaction and state why this is so.
(ii) If it is not acceptable, what should be done to improve the compaction so
that it will meet the specification?
Fig. Laboratory compaction curve(b) An embankment will be constructed to have a final volume of 4,5x0m3(x is the
last digit of your student number). From the Standard Proctor test, the maximum dry
density and the optimum moisture content of the fill is 1900kgm3 and 12% respectively.
The bulk density and moisture content of the soil at the borrow area are 1500kgm3 and
10.5%. The Relative Compaction required is referred to that for the "fill material"
described in the General Specification for civil engineering, clause 6.48.
Estimate the cost of excavation if the cost is $20 per m3.(Assume the cost is based
solely on the volume of the soil excavated from the borrow area).
Q.2 A site is underlain by a layer of normally consolidated clay 6m thick. In order to
minimize settlement, a pre-loading pressure is used to pre-load this site. The
average effective overburden pressure at the middle of the clay layer at present is
100kPa. The increase of pressure due to the permanent design load for the site is
120kPa. The clay is bounded by a layer of sand above and impermeable layer
below. The other parameters of the clay are given below:
(a) Determine the time in months required to load the site if primary consolidated
settlement is to be eliminated for a given total pre-compression pressure of
200kPa,
(b) If the pre-compression cannot be completed in 9 months, provide vertical
drains, together with the preloading, to speed up the consolidation such that only
9 months of preloading is allowed. Assume CV=Cr. Radius of sand drain to be
100mm. Using the same preloading pressure, design the optimal spacing of the
vertical drain.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Civil Engineering Questions!