Question: For a particular project, activities required to complete the project, the precedence relationships for the activities, and activity time estimates, as shown in the following
For a particular project, activities required to complete the project, the precedence relationships for the activities, and activity time estimates, as shown in the following table:
Activity Activity Predecessor Time Estimates Weeks
a m b
A
B
C $
D B C $
E A B
F E D
G E F
a Draw the network diagram and show all calculations for ESEFLSLF and Slack. You will have to find the expected time and variance for each activity.
b Identify the critical path by highlighting and find out the estimated project completion time, ET and the standard deviation for the project completion time, s
c Determine the probability that the project will be completed in weeks or less.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock