Question: For a particular project, activities required to complete the project, the precedence relationships for the activities, and activity time estimates, as shown in the following
For a particular project, activities required to complete the project, the precedence relationships for the activities, and activity time estimates, as shown in the following table:
tableActivity,Time Estimates WeeksActivityPredecessor,ambABCDB CEA BFE DGE F
a Draw the network diagram and show all calculations for ESEFLSLF and Slack. You will have to find the expected time and variance for each activity.
b Identify the critical path by highlighting and find out the estimated project completion time, and the standard deviation for the project completion time,
c Determine the probability that the project will be completed in weeks or less.
d What is the probability that the project will take more than week
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock