Question: For a project, the following earned value data have been assessed: AC: $4,000,000 CV: $-500,000 SPI: 1.12 BAC: $9,650,000 What is the earned value of

For a project, the following earned value data

For a project, the following earned value data have been assessed: AC: $4,000,000 CV: $-500,000 SPI: 1.12 BAC: $9,650,000 What is the earned value of the project? $3,000,000 $3,500,000 $4,480,000 %5,650,000