Question: For a project with an expected completion time of 15 weeks, a target completion of 18 weeks, and project standard deviation of 1.95 weeks, we

For a project with an expected completion time of 15 weeks, a target completion of 18 weeks, and project standard deviation of 1.95 weeks, we want to estimate the probability of competing by the target. The first step is to compute the Z-score of the target date given preceding information. What is the Z-score of the target date